SMRP metric 5.4.4
Schedule Compliance Formula (Work Orders)
The short-form equation is (Nsc / Ns) × 100. Every symbol is defined in the variable key below.
Count-based schedule compliance. Read it alongside the hours form (5.4.3).
(Nsc / Ns) × 100
Nsc = scheduled work orders completed · Ns = total scheduled work orders
Ex. 45 of 50 scheduled work orders were completed → 90%. Read this next to the hours form (5.4.3).
Edition note. The formula on this page follows the 7th edition of SMRP Best Practices. Where we know the 6th and 7th editions differ, we say so on the relevant metric pages. If a question quotes a formula, use the formula in the question.
This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.
Frequently asked questions
Is work-order schedule compliance the same as the hours form?
No. 5.4.4 is a count of scheduled work orders completed. 5.4.3 is based on hours. A short job and a long job count the same in 5.4.4, so the hours form is the better picture of whether the week’s capacity was used as scheduled.