SMRP metric 5.4.8 · Revised in the 7th edition

Planned backlog (SMRP Metric 5.4.8)

The short-form equation is (Wp + Wr) / C. Every symbol is defined in the variable key below.

Weeks of planned-plus-ready work in front of the crew.

(Wp + Wr) / C

Wp = planned work hours still open  ·  Wr = ready-to-schedule hours  ·  C = weekly crew capacity (hours). Result is in crew-weeks.

Ex. (1,200 + 400) / 400 = 4.0 weeks.

Edition note. This metric is listed as revised in the 7th edition of SMRP Best Practices. The formula on this page is the 7th-edition form. The exam may still use earlier wording, so if a question quotes a formula, use the formula in the question. Unconfirmed 6th-edition equations are not shown.

This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.

Practice this metric in exam-style questions

The free diagnostic and the $99 practice-exam pack include original calculation and definition items. They are not official exam questions.

Independent exam prep · Not affiliated with SMRP