SMRP metric 5.4.3
Schedule Compliance Formula (Hours)
The short-form equation is (Hs / Ha) × 100. Every symbol is defined in the variable key below.
Hours of the weekly schedule that were actually worked, versus hours that were available to schedule.
(Hs / Ha) × 100
Hs = scheduled work performed · Ha = total time available to schedule
Ex. 720 scheduled hours were actually worked, of 800 hours available to schedule → 90%.
Edition note. The formula on this page follows the 7th edition of SMRP Best Practices. Where we know the 6th and 7th editions differ, we say so on the relevant metric pages. If a question quotes a formula, use the formula in the question.
This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.
Frequently asked questions
Which schedule-compliance formula should I use, hours or work orders?
Metric 5.4.3 is the hours form: scheduled hours worked over hours available to schedule. Metric 5.4.4 is the count of scheduled work orders completed. Read them together. A site can look good on counts and still miss a large share of the hours.