SMRP metric 5.4.2 · Revised in the 7th edition

Proactive work (SMRP Metric 5.4.2)

The short-form equation is (Hpr / Hm) × 100. Every symbol is defined in the variable key below.

Share of hours spent on work started before failure (PM, PdM, and planned corrective).

(Hpr / Hm) × 100

Hpr = proactive hours  ·  Hm = total maintenance hours

Ex. 5,600 hours started before failure, of 8,000 total → 70% proactive.

Edition note. This metric is listed as revised in the 7th edition of SMRP Best Practices. The formula on this page is the 7th-edition form. The exam may still use earlier wording, so if a question quotes a formula, use the formula in the question. Unconfirmed 6th-edition equations are not shown.

This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.

Practice this metric in exam-style questions

The free diagnostic and the $99 practice-exam pack include original calculation and definition items. They are not official exam questions.

Independent exam prep · Not affiliated with SMRP