SMRP metric 5.4.1 · Revised in the 7th edition

Reactive Work Formula (SMRP Metric 5.4.1)

The short-form equation is (Hbr / Hm) × 100. Every symbol is defined in the variable key below.

Share of hours spent on work that broke into the schedule. Not the same as unplanned %.

(Hbr / Hm) × 100

Hbr = break-in hours  ·  Hm = total maintenance hours

Ex. 1,600 break-in hours of 8,000 total maintenance hours → 20% reactive. A job can be planned and still be reactive if it broke into the schedule.

Edition note. This metric is listed as revised in the 7th edition of SMRP Best Practices. The formula on this page is the 7th-edition form. The exam may still use earlier wording, so if a question quotes a formula, use the formula in the question. Unconfirmed 6th-edition equations are not shown.

This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.

Frequently asked questions

Can planned work also be reactive?

Yes. Reactive work counts break-in hours. If a job had a plan but still broke into the weekly schedule, it can show up as reactive. Unplanned work is a different metric: hours that never had a plan.