SMRP metric 3.4 · Revised in the 7th edition

Unscheduled Downtime Percent (SMRP Metric 3.4)

The short-form equation is Tun = Σ downtime not on the weekly schedule. Every symbol is defined in the variable key below.

Downtime for repairs or changes that were not on the finalized weekly schedule.

Tun = Σ downtime not on the weekly schedule

Unscheduled downtime (%) = Tun / Ta × 100.

Ex. 62 h unscheduled in a 720 h month → 8.6%.

Edition note. This metric is listed as revised in the 7th edition of SMRP Best Practices. The formula on this page is the 7th-edition form. The exam may still use earlier wording, so if a question quotes a formula, use the formula in the question. Unconfirmed 6th-edition equations are not shown.

This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.

Practice this metric in exam-style questions

The free diagnostic and the $99 practice-exam pack include original calculation and definition items. They are not official exam questions.

Independent exam prep · Not affiliated with SMRP