Total downtime (SMRP Metric 3.2)

The short-form equation is Td = Tsch + Tun. Every symbol is defined in the variable key below.

All time the asset is not capable of running, scheduled plus unscheduled.

Td = Tsch + Tun

Total downtime (%) = Td / Ta × 100. Tsch = scheduled downtime  ·  Tun = unscheduled downtime.

Ex. 50 + 62 = 112 h in a 720 h month → 15.6%.

Edition note. This metric is listed as revised in the 7th edition of SMRP Best Practices. The formula on this page is the 7th-edition form. The exam may still use earlier wording, so if a question quotes a formula, use the formula in the question. Unconfirmed 6th-edition equations are not shown.

This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.

Practice this metric in exam-style questions

The free diagnostic and the $99 practice-exam pack include original calculation and definition items. They are not official exam questions.

Independent exam prep · Not affiliated with SMRP