SMRP metric 4.1

Rework Formula (SMRP Metric 4.1)

The short-form equation is Rework % = (Hrw / Hm) × 100. Every symbol is defined in the variable key below.

Share of all maintenance labor spent fixing premature failures caused by maintenance, operations, or material quality.

Rework % = (Hrw / Hm) × 100

Hrw = corrective hours identified as rework  ·  Hm = total maintenance labor hours

Ex. 36 h rework in 1,200 h → 3.0%. Denominator is total maintenance hours, not only corrective hours.

Edition note. The formula on this page follows the 7th edition of SMRP Best Practices. Where we know the 6th and 7th editions differ, we say so on the relevant metric pages. If a question quotes a formula, use the formula in the question.

This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.

Practice this metric in exam-style questions

The free diagnostic and the $99 practice-exam pack include original calculation and definition items. They are not official exam questions.

Independent exam prep · Not affiliated with SMRP