PM and PdM Work-Order Compliance (SMRP 5.4.10)

The short-form equation is Variance = (fact / fpl) × 100 − 100. Every symbol is defined in the variable key below.

How far completed PM/PdM intervals drifted from the plan, sliced by criticality.

Variance = (fact / fpl) × 100 − 100

fact = actual frequency (interval achieved)  ·  fpl = planned frequency. Report the share of PM/PdM work orders in each variance band, by criticality rank — not a single on-time percent. That single on-time percent is 5.4.14.

Ex. done at 40 days vs a 30-day plan → (40/30)×100 − 100 = 33% overdue variance.

Edition note. The formula on this page follows the 7th edition of SMRP Best Practices. Where we know the 6th and 7th editions differ, we say so on the relevant metric pages. If a question quotes a formula, use the formula in the question.

This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.

Frequently asked questions

Is 5.4.10 the same as PM and PdM compliance (5.4.14)?

No. 5.4.14 is the simple on-time percent: work orders done on time over work orders due. 5.4.10 is officially a variance form, not that simple ratio. If a question asks for 5.4.10, do not grab the 5.4.14 formula.