SMRP metric 5.4.14
PM and PdM Compliance Formula (SMRP 5.4.14)
The short-form equation is Ndone / Ndue. Every symbol is defined in the variable key below.
On-time completion of PM/PdM work orders. This is the simple compliance percent; 5.4.10 is the interval-variance view.
Ndone / Ndue
Ndone = completed by the due date or an agreed grace rule · Ndue = PM/PdM work orders due. Define grace if used: due date, +1 day, or +20% of frequency (max 28 days).
Target often shown as 100% — a target, not a definition.
Edition note. The formula on this page follows the 7th edition of SMRP Best Practices. Where we know the 6th and 7th editions differ, we say so on the relevant metric pages. If a question quotes a formula, use the formula in the question.
This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.
Frequently asked questions
Is this the same as metric 5.4.10?
No. 5.4.14 is the simple on-time percent. 5.4.10 is a variance form. Candidates often mix the two. Use the metric number in the question.