SMRP metric 5.3.5
Planning variance index (PVI) (SMRP Metric 5.3.5)
The short-form equation is N±10% / Npl. Every symbol is defined in the variable key below.
Hit rate for planning estimates, using a ±10% cost band.
N±10% / Npl
N±10% = planned work orders whose actual cost landed within ±10% of plan · Npl = total planned work orders
Ex. 70 of 100 planned work orders closed within ±10% of the planned cost → PVI = 0.70.
Edition note. The formula on this page follows the 7th edition of SMRP Best Practices. Where we know the 6th and 7th editions differ, we say so on the relevant metric pages. If a question quotes a formula, use the formula in the question.
This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.