SMRP metric 5.3.4 · Revised in the 7th edition

Actual hours to planning estimate (SMRP Metric 5.3.4)

The short-form equation is Hact / Hpl. Every symbol is defined in the variable key below.

Labor-hour performance of planned jobs, same reading as 5.3.3.

Hact / Hpl

Hact = actual hours  ·  Hpl = planned hours

Ex. Actual hours 44 on a 40-hour plan → 1.10.

Edition note. This metric is listed as revised in the 7th edition of SMRP Best Practices. The formula on this page is the 7th-edition form. The exam may still use earlier wording, so if a question quotes a formula, use the formula in the question. Unconfirmed 6th-edition equations are not shown.

This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.

Practice this metric in exam-style questions

The free diagnostic and the $99 practice-exam pack include original calculation and definition items. They are not official exam questions.

Independent exam prep · Not affiliated with SMRP