SMRP metric 5.1.4 · Revised in the 7th edition
Preventive maintenance hours (SMRP Metric 5.1.4)
The short-form equation is (Hpm / Hm) × 100. Every symbol is defined in the variable key below.
Share of maintenance labor spent on preventive work.
(Hpm / Hm) × 100
Hpm = preventive maintenance hours · Hm = total maintenance labor hours
Ex. 1,600 preventive hours of 8,000 total maintenance hours → 20%.
Edition note. This metric is listed as revised in the 7th edition of SMRP Best Practices. The formula on this page is the 7th-edition form. The exam may still use earlier wording, so if a question quotes a formula, use the formula in the question. Unconfirmed 6th-edition equations are not shown.
This page is study material for the closed-book CMRP exam. It is not official SMRP text. Learn the short-form equation and the variable key well enough to write them from memory.